Access road of S. Francisco beach with a length of 2,6km, with 1x1 lanes with 0,5m (side) + 3,5m (lane) + 3,5m (lane) + 0,5m (side). The works included earthwork, basalt stone masonry, drainage, paving and signaling (vertical and horizontal). Six metallic and concrete water passages with diameters varying between 0,315 and 1 meter were executed, one of which consists of a 10 battery of 1-meter diameter; support walls in local mortar stone; ditches with widths between 0,6m and 1,0m. About 32.000m3 were excavated, 15.000m3 of landfills were placed, about 6.000m3 of ABGE were placed in a 20cm base layer, and 24.540m2 of bituminous mixtures were placed in a 5cm thick wear layer. This work included 3 roundabouts to give direct access to the beach of S. Francisco and the Sambala urbanization.
Supervision, quality control and geometric control.